S.E.A.S. RESTORATION & REPAIRS AFTER FLOOD DUE TO BURST PIPES
3-17-2025 Staff walk-through after work on repair for the day was over. 4:05pm
3-17-2025 Cabinet bases are being installed in the sacristy and the priest vesting area. 2:38pm
3-16-2025 Avila Cabinetry, a subcontractor of Arnold Builders, came on Sunday to take measurements. 11:48am
3-14-2025 No work today. This is the church interior with the altar extension added. It will remain in this rough format until the crew until the electrician can come to work on the outlets next week. 8:15am
3-13-2024 Extending the altar forward about a foot so that the electrical boxes can be extended upwards to keep them from ever being covered with standing water in the future. 11:00am
3-12-2025 With repairs completed to one of the Stations, the eight remaining stations were replaced on the church walls in preparation for this Friday's Stations of the Cross. 7:30pm
3-12-2025 Restoration of Stations of the Cross continued today (A couple were put up the night before.) while our office manager, Javier Soto Osorio waited for our contractor, Arnold Builders, and his crew to plan out the next phase of the repair project. While Mr. Arnold was present, Javier and he disassembled the cross from the roof so that the cross portion could be taken so a new base could be prepared for it. The base of the cross had abundant wood rot and was discarded. 12:14 pm
3-10-2025 Some of the cabinets like the cleaning supply room and this cabinet for liturgical items have been given new, raised shelving. 2:35pm
3-8-2025 Our sparsely decorated altar on wheels reminds us that we are still in construction. This is the first weekend in weeks that we are able to use both sides of the church for seating at Mass. 3:58pm
3-7-2025 Office manager, Javier, plans the location of the Stations of the Cross and begins to mark the walls with the use of a laser level. 7:30pm
3-6-2025 The Best Buy Geek Squad reinstalled our TV monitors in the church. They also moved another TV monitor from one room in the office to another so that it could be better used by our catechism classes among others. 10:00am
3-2-2025 Staff prepares the pews for weekday construction. 3:35pm
2-27-2025 Staff walk-through a few hours after the workers had left and walls had dried a bit. Painting is complete. The next phase of construction can begin. 4:50pm
2-27-2025 This is the final coat of paint being applied to the church interior. All that was left to paint as staff came through at this time was a corner of the church and the family room with glass window and its adjacent storage room. The painting will be complete today. 10:50am
2-27-2025 Painting continues this beautiful Thursday morning. 8:50am
2-26-2025 ...and more painting. Workers left at 4:00pm. 4:15pm
2-26-2025 ...and painting...11:06am
2-26-2025 Painting... 8:35am
2-25-2025 Painting window ledges. This type of small work before the walls are painted. 3:15pm
Staff did a walk through after workers had been gone for almost an hour. 4:01pm
Staff did a walk through after workers had been gone for almost an hour. 4:01pm
2-25-2025 Continuing primer and adding paint to corners and window ledges. 2:23pm
2-25-2025 Applying the primer coat to the walls. 1:09pm
2-25-2025 Preparing the walls for paint by taking off old tacks, nails, screws, and adhesive tape, then filling in the many holes left from nails and screws. 8:40am
2-23-2025 From Mass to Construction prep, because you have asked: Our office staff has a good weekly routine for removing the altar furnishings into their proper places within our temporary sacristy and community room, then covering the pews, computer tables, and tabernacle. No longer finishing after sunset, we have shaved off over an hour from when we first began preparing the church for construction workers during the week. (The first weekend had volunteers, but subsequent weeks have only been staff.) Photos of taping of protective plastic from 3:30 to 5:00pm.
2-20-2025 Texturing completed on interior wall along large parking lot and left to dry. 11:25am
2-20-2025 Texturing along main entrance wall was smoothed down. 8:45am
2-19-2025 Texturing completed along Western wall near the main door and partially done along long wall on the side of the large parking lot. Our contractor was briefly present to check on progress and to plan with subcontractor. 2:12pm
2-19-2025 Texturing applied to southern interior wall from the kitchen door to the sacristy. 8:54am
2-18-2025 Texturing applied to the walls of the three side rooms where new wall board was placed. 4:35pm
2-18-2025 Preparing to texture beginning with the storage room. 10:45am
2-18-2025 Priming of the walls. 9:45am
2-17-2025 Plastering metal corner guards and retouch with plaster. 1:56pm
2-17-2025 Metal corner protector installation continues. 9:45am
2-12-2025 TV Monitors removed. Wall board application complete and plastering done. 11:40am
2-11-2025 Drywall cut and put in place. 2:00pm
2-7-25 Drywall installation & drywall mud, 2:47 pm
2-7-25 Pastor's visit of workers & drywall installation, 9:47 am
2-6-25 Sacristy pipes adjustment
2-5-25 Insulation installation
2-5-25 Diocese of Monterey's Facilities and Safety Manager, Robbie Parry, visited and inspected church campus and on-going repairs.
2-5-25 "Floorshell" laid out.
2-4-25 Thank you, Jon, for wrapping the pews, furniture, and computers.
2-3-25 Clearing of Sanctuary